Setting up the soil washing plant.
Published on 01/07/2021
The new remediation company, ARGE MZ Hueningen (comprising Marti Infra AG, Marti AG, Züblin Umwelttechnik GmbH and Strabag Umwelttechnik GmbH), conducted a review of the remediation site and what caused the shutdown, before the work was commissioned.
The review found that during the initial remediation phase, soil had been stored outside the tents, the barge had no containment system, the soil-washing plant operated in the open air and the existing tents were not sufficiently airtight. The issue with the tents had contributed to the odor development and issues in 2013. Note that the initial site setup and approach was aligned with the prefectural order of 2012.
To ensure that work could be carried out without generating dust, each work step was validated by air monitoring before the step was carried out. It took about a year to validate the revised remedial measures to ensure that all the lessons learned had been addressed.